Kingsbridge Traffic Closures Disrupt Local Operations

Construction of a new school and housing complex will restrict access on Review Place through the end of 2026.

Updated on Oct. 15, 2026 in Construction

Isometric editorial illustration of a construction crane and steel beams on a city street, illustrating urban development infrastructure.
Logistical delays for local businesses in Kingsbridge persist as major school and residential construction projects restrict traffic through late 2026. AI Illustration. Upload story photo >

Live Poll

Do you support the construction of new high-density residential and school projects in your community?

Construction is underway on a new 100,000-square-foot elementary school and a 279,000-square-foot residential complex in Kingsbridge. The project, which involves traffic closures on Review Place through late 2026, will introduce 700 student seats and 339 apartments to the former Church of the Visitation site.

Why it matters

The development transforms a long-vacant religious property into a high-density mixed-use hub, creating significant immediate logistics challenges for businesses operating near the Review Place construction site.

The development adds 339 apartments and a 700-student school to the Kingsbridge neighborhood. This 279,000-square-foot residential project reserves 53 units for supportive housing while catering to households earning between 40% and 105% of the area median income.

The players

New York City School Construction Authority

Government entity responsible for the design, construction, and renovation of schools throughout New York City.

Tishman Speyer

Global real estate developer, owner, and operator known for large-scale commercial and residential projects.

The details

The New York City School Construction Authority is managing the 100,000-square-foot school, while Tishman Speyer is developing the adjacent residential complex. To facilitate construction at 3850 Review Place and 160 Van Cortlandt Park South, the city has restricted traffic on Review Place. Operators in the immediate vicinity should anticipate ongoing logistical delays as heavy equipment access continues for the next 14 months.

Timeline

  1. 2015: Church of the Visitation parish merged with St. John's.

  2. 2022: Tishman Speyer acquired the property.

  3. Weekdays 8 a.m. to 6 p.m. through Dec. 26, 2026: Review Place is closed to through traffic.

  4. Fall 2027: School opening and residential construction completion.

Market Landscape

This development follows the pattern set by New York City's inclusionary zoning policies, which incentivize developers to integrate affordable units within major residential projects. It repurposes a vacant religious site into high-density community and residential infrastructure.

Local businesses should plan for continued delivery and logistics disruptions on Review Place through December 2026. Monitor the site's progress for potential shifts in local consumer foot traffic once the school and 339-unit complex open in 2027.

The takeaway

The project signals a significant densification of the Kingsbridge area that will alter regional supply chain access. Operators should update their distribution schedules to account for weekday traffic closures on Review Place until at least the end of 2026.

Further reading

For more on industry shifts in local development, visit Construction.

Source note: This article includes information reported by The Riverdale Press.