TDOT Identified Nashville Properties for Highway Expansion
Owners and operators along the I-24 corridor must navigate property acquisition steps as highway construction begins.
Updated on Oct. 14, 2026 in Openings & Closings

Live Poll
Do you trust local government to balance community needs with large-scale infrastructure expansion in your area?
The Tennessee Department of Transportation (TDOT) identified 29 single-family homes, four duplexes, and 18 businesses for relocation to clear a path for the I-24 Choice Lanes project. These acquisition efforts were initiated by state officials throughout the summer of 2026.
Why it matters
The project requires significant right-of-way expansion, forcing property owners and local businesses to negotiate land acquisition terms or relocate operations. This process directly impacts real estate stability and long-term site planning for firms situated along the I-24 corridor.
TDOT has moved to acquire 18 businesses and 33 residential properties for the I-24 Choice Lanes expansion. While 20 townhomes were removed from the initial relocation list, the department continues to coordinate with impacted owners via assigned consultants.
The players
Tennessee Department of Transportation
The state agency responsible for planning, building, and maintaining the Tennessee highway and transit infrastructure.
DriveTN
The designated private-sector partner managing the delivery and operational rollout of the I-24 Choice Lanes project.
Boswell's Harley-Davidson
A local retail business that occupied a site on Fesslers Lane before closing as part of the project acquisition.
The details
TDOT uses assigned right-of-way consultants to manage the transition for each affected property owner and business tenant. Affected parties received multiple rounds of correspondence starting in June 2026, including certified mail, UPS Next Day Air, and formal appraiser evaluations to establish property valuations. While Boswell's Harley-Davidson on Fesslers Lane has already closed, other businesses must finalize relocation agreements as part of the state's broader highway infrastructure strategy.
Timeline
June 23, 2026: Initial property acquisition letters were sent.
July 17, 2026: Signed follow-up letters were sent via UPS.
August 19, 2026: DriveTN was announced as the Choice Lanes partner.
Market Landscape
This land acquisition phase follows the established pattern of major highway infrastructure projects in Tennessee. It marks a shift from planning to execution for the I-24 Southeast Choice Lanes project, impacting local commercial footprints across the corridor.
Operators in the I-24 corridor should confirm their property's status relative to current right-of-way maps and review all correspondence from state consultants. Business owners facing displacement must prioritize finalizing appraisals and identifying viable relocation sites to minimize operational downtime.
The takeaway
Large-scale infrastructure projects create significant displacement risks for local businesses that require early proactive planning. Affected property owners should maintain a thorough record of all communications from state consultants and engage counsel to ensure that appraisal valuations align with current market conditions.
Further reading
For more information on local development trends, visit Nashville Openings & Closings.