Polish shipping company Chipolbrok began the maiden voyage of the 182-meter vessel Chełmoński, carrying 11 wind turbine sets from China to South Africa. The vessel is the first of a four-ship Matejko class built for dual-fuel-ready Far East-Europe and Africa service.
Why it matters
The voyage tests a new heavy-lift bulk carrier design that combines deck cranes with dual-fuel readiness, a capability relevant to operators moving project cargo such as renewable energy equipment. The vessels also prepare Chipolbrok for the eventual retirement of four older Orkan-class ships.
The Chełmoński carries 11 wind turbine sets on a 182-meter, 38,000 dwt hull fitted with three 350-ton deck cranes for a combined 700-ton tandem lift. The four-vessel Matejko class is set to replace an equal number of older Orkan-class ships in Chipolbrok's fleet.
The players
Chipolbrok
A Polish shipping company operating bulk and project-cargo vessels on Far East-Europe and Africa routes, now expanding its fleet with dual-fuel-ready ships.
HongFa Shipping
A Shanghai-based shipping company and sister firm of Chipolbrok that has chartered the Chełmoński.
ZPMC
A Chinese shipyard in Qidong that is building the Matejko-class vessels for Chipolbrok.
The details
Each vessel uses a forward-positioned superstructure to free up cargo space and carries three 350-ton deck cranes that can work in tandem for heavy lifts. Chełmoński loaded its first cargo at the Chinese ports of Taicang and Dongzao before sailing toward Saldanha Bay, with the voyage ending at Lobito, Angola. The ship is chartered to HongFa Shipping, a Shanghai-based sister company of Chipolbrok.
Timeline
May 2026: Chełmoński and sister ship Wyspiański were launched.
September 2026: Chełmoński was commissioned.
Early November 2026: Discharge operations are expected to begin at Saldanha Bay.
Market Landscape
The Matejko-class ships mark a fleet renewal for Chipolbrok, with the first two vessels launched in May 2026 and built at a Chinese yard. The design pairs heavy-lift deck cranes with a forward superstructure, a configuration suited to the project cargo that Chipolbrok is carrying.
Operators shipping heavy or project cargo to Africa should watch whether crane-equipped, dual-fuel-ready tonnage becomes available on these routes. Logistics and procurement teams planning renewable-energy equipment shipments can use this voyage as an early read on the capacity and scheduling options emerging on Far East-to-Africa lanes.
The takeaway
Freight buyers moving heavy equipment should track the Lobito and Saldanha Bay discharge timelines and consider whether crane-equipped tonnage fits their upcoming shipping windows. Monitoring the Wyspiański's first European calls will show whether the Matejko class is entering regular service.
What happens next
Discharge operations at Saldanha Bay are expected to begin in early November 2026, and Wyspiański is preparing to enter Far East-Europe service with planned calls in Turkey, Antwerp and Hamburg.