Defense Device Security Rollouts Lag Behind Schedule
Contractors connecting devices to defense networks should expect uneven C2C enforcement, with some components projecting completion into 2027.
Updated on Nov. 4, 2026 in Military Jobs

The Department of War Office of Inspector General found that none of six audited components completed all 37 Comply-to-Connect tasks by the Sept. 30, 2025 deadline. Auditors report the gaps affect defense contractors and military suppliers that depend on the network's device-security requirements.
Why it matters
Comply-to-Connect requires devices to be authenticated before they join military networks, so incomplete rollouts leave gaps that affect how vendors and contractors connect to defense systems. The audit was released Oct. 26, nearly a month after the original deadline passed, and components are still projecting completion dates into 2027.
Auditors measured six components against 37 Comply-to-Connect tasks, and as of June USNORTHCOM still had 33 outstanding, the largest gap of the group. The Department of War requested $3.3 billion for C2C and zero trust efforts from FY2021 through FY2025.
The players
Department of War Office of Inspector General
The internal oversight office of the Department of War that audits defense components and issues recommendations on network and device security compliance.
U.S. Northern Command (USNORTHCOM)
The combatant command responsible for homeland defense and defense support of civil authorities, operating a continuous network that the audit flagged for its largest task gap.
U.S. Transportation Command (USTRANSCOM)
The combatant command that manages global military logistics and transportation, including the cloud migration whose delay the audit identified.
Defense Health Agency (DHA)
The Department of War agency that manages the Military Health System, including its hospitals, clinics, and health IT systems.
Defense Finance and Accounting Service (DFAS)
The Department of War agency that handles military pay, civilian pay, and contractor payment processing across the defense enterprise.
The details
During on-site testing, auditors connected a compliant but unauthorized laptop, phone, and USB drive to networks at five components. Tools at four of those components detected and interrogated the devices, while one component's tool did neither. Army administrators said their focus was moving devices onto an Army enterprise network, while USNORTHCOM's Joint Operations Center rejected changes it said could interrupt the command's around-the-clock operations.
Timeline
Sept. 30, 2025: Deadline for Steps 1-4 of the C2C implementation plan passed.
June: Outstanding task counts were recorded for each component.
Oct. 26: The DOW Inspector General released the audit report.
Sept. 14: USTRANSCOM targeted completion of its interim process.
Nov. 30: USNORTHCOM expects to finish remaining installations.
Market Landscape
Comply-to-Connect is the Department of War's device-authentication framework, and this audit shows its implementation lagging the plan's own schedule across the Army, Navy, and several combatant commands. The $3.3 billion requested for C2C and zero trust from FY2021 through FY2025 places the program among the larger ongoing investments in defense network security.
Contractors and vendors supplying devices or software to defense components should expect continued device-authentication requirements and verify their products against C2C standards before enrollment. Operators in the defense supply chain should track component-level completion dates, since timelines vary from Navy's three open tasks to USNORTHCOM's 33.
The takeaway
Treat the Comply-to-Connect schedule as a moving target: any business selling into defense networks should confirm which component it serves and how far that component's rollout has progressed. Check each component's published completion date before committing to delivery or integration timelines.
What happens next
USNORTHCOM expects to finish its remaining installations by Nov. 30, and USTRANSCOM expects to meet C2C requirements by June 2027, both of which will show whether the audited gaps are closing on schedule.
Further reading
For context on the defense workforce and contracting roles tied to military IT programs, see Military Jobs.
Source note: This article includes information reported by Executive Gov.