Alaska Backs Enstar Bid for Kenai Loop Gas Storage
The proposed $240 million storage facility aims to secure heating supply for the region as local gas production declines.
Updated on Oct. 22, 2026 in Oil and Gas

Live Poll
Should regulators prioritize the most technically prepared company for critical local energy infrastructure projects?
The Alaska Division of Oil and Gas has issued a preliminary finding supporting Enstar Natural Gas Co.'s application to utilize the Kenai Loop gas field for storage. The project aims to address declining gas production in the Cook Inlet basin by increasing capacity for winter heating demand.
Why it matters
Enstar requires an advance determination of prudency from the Regulatory Commission of Alaska to secure the $240 million in project financing needed for the development. As regional gas production falls, expanding storage capacity has become critical for managing seasonal demand profiles and potential LNG imports.
The proposed investment in the Kenai Loop storage facility totals $240 million. This project is intended to bolster winter heating supply in the Cook Inlet basin, where gas production is currently in decline.
The players
Enstar Natural Gas Co.
A natural gas utility provider operating in Alaska that is seeking to expand its infrastructure through the Kenai Loop project.
Alaska Division of Oil and Gas
The state agency responsible for managing oil and gas leases and issuing preliminary findings on land use.
Regulatory Commission of Alaska
The body tasked with ruling on the prudency of utility investments and utility rate determinations.
Hilcorp Cook Inlet
An oil and gas exploration and production company that also submitted a competing lease proposal for the Kenai Loop field.
The details
Enstar plans to repurpose the depleted Upper Tyonek Pool reservoir and utilize existing oil field facilities at the Kenai Loop site, which regulators noted was supported by more robust technical information than a competing proposal from Hilcorp Cook Inlet. While Hilcorp proposed constructing new well pads and drilling new wells, Enstar's approach relies on leveraging existing infrastructure. To move forward, Enstar has filed for a storage injection order and is seeking a prudency ruling that is essential for its financing strategy.
Timeline
October 22, 2026: Preliminary lease finding issued by the Alaska Division of Oil and Gas.
Market Landscape
This move highlights the competitive race for storage capacity as regional production declines in the Cook Inlet basin. Enstar is currently navigating the Alaska Oil and Gas Conservation Commission storage injection order protocols to finalize its facility plans.
Operators in the energy and utility sector should track the outcome of the pending prudency determination, as it will signal the regulatory appetite for financing storage retrofits versus new drilling. The shift toward repurposing depleted reservoirs could provide a model for mitigating regional supply gaps during peak heating months.
The takeaway
The move underscores the growing operational priority of maintaining consistent winter heating supply as legacy production wells in the Cook Inlet basin face decline. Owners should monitor future Regulatory Commission of Alaska meetings for the final prudency determination, which is the final gate for project funding.
Further reading
For more on how infrastructure projects are reshaping energy supply in the region, visit Alaska Oil and Gas.
Source note: This article includes information reported by Petroleum News.