Ramsay-McCormack Site Shifts to Public Library
Ensley contractors and commercial operators tied to the stalled $20 million project should plan for a delayed, uncertain timeline.
Updated on Nov. 7, 2026 in Openings & Closings

Live Poll
Do you trust your local government to finish long-delayed community projects?
Birmingham Mayor Randall Woodfin announced plans to build a public library on the Ramsay-McCormack site in Ensley, replacing a delayed $20 million redevelopment that had been expected to bring nearly 190 jobs. The city must first regain control of the property from previous developers and present its new proposal to the Birmingham City Council.
Why it matters
The original project stalled through repeated funding problems and a court-ordered timeline, and the developer's death in August 2026 led the remaining partners to stop pursuing it. For local operators, the shift means a public use replaces a planned commercial development, removing the expected job base and construction demand the original plan promised.
The original $20 million, five-story project was expected to create nearly 190 jobs, while the site's earlier 10-story building was demolished in 2021. A judge gave the city 60 days to finalize its plans, and the new library's cost and scope have not been published.
The players
City of Birmingham
The Alabama city's government controls the Ramsay-McCormack property and is pursuing the public library project as the new developer of record.
Randall Woodfin
Birmingham's mayor, who announced the plan to build a public library on the Ramsay-McCormack site.
Birmingham City Council
The city's legislative body, which must review and approve the new proposal before the library project can advance.
The details
The city must first regain control of the Ramsay-McCormack property from the previous developers before it can proceed. Once that is resolved, Birmingham must present its new proposal to the Birmingham City Council for approval. Construction on the new development is projected to begin during the fourth quarter of 2027.
Timeline
Nov. 5, 2026: Mayor Woodfin announced the library plan.
Aug. 2026: Developer Irvin Henderson died.
2021: The original 10-story building on the site was demolished.
Feb. 3, 2027: Next court hearing scheduled.
Fourth quarter of 2027: Projected start of construction.
Market Landscape
The original project was bound by court-ordered start and completion deadlines in 2017 and 2019, which it did not meet before the building was demolished in 2021. The new public library plan marks a shift from a privately led commercial redevelopment to a city-led public use on the same site.
Operators in Ensley and adjacent commercial corridors should not count on the original $20 million development's jobs or construction spending, since the site is moving to public use. Contractors and vendors who had planned for the project should treat the timeline as uncertain until the City Council acts on the new proposal.
The takeaway
The stalled project shows how a single developer's death can unwind a redevelopment plan that court orders and funding gaps had already delayed for years. Operators tracking Ensley development should watch the February 2027 court hearing and the City Council's review of the library proposal.
What happens next
The city must present its new library proposal to the Birmingham City Council and provide an update to the court within 60 days, with the next court hearing scheduled for Feb. 3, 2027.
Further reading
For more on projects like this, see Openings & Closings coverage in Birmingham.
Source note: This article includes information reported by WVTM 13.