Large Power Users Get Faster Grid Access in California
Operators of 50 MW-plus facilities can connect sooner but must accept curtailment when power supplies run critically low.
Updated on Nov. 2, 2026 in Utilities

The California Independent System Operator board approved a large-load interconnection proposal for customers 50 MW and over, letting them join the grid while network upgrades are pending. The proposal is slated for filing with federal regulators on November 16, 2026, and affects data centers and other heavy power users in the state.
Why it matters
Large power users now have a defined, expedited path onto the grid, but they accept curtailment when supplies run critically low and must ride through system disturbances. The move follows a 2020 federal order directing grid operators to remove barriers to distributed energy resource participation.
The threshold for large-load classification is 50 MW, and the proposal is set for filing with FERC on November 16, 2026. The extraction does not report how many California customers meet the threshold.
The players
California Independent System Operator (CAISO)
The nonprofit grid operator that manages the high-voltage transmission system and wholesale electricity markets for most of California.
ISO New England
The regional grid operator for six New England states, responsible for wholesale electricity markets and reliability planning across the region.
Federal Energy Regulatory Commission (FERC)
The federal agency that regulates interstate electricity transmission and wholesale power markets and oversees the rules grid operators must follow.
The details
Under the proposal, large-load customers can connect to the grid on an expedited basis while the network upgrades they depend on are still pending. In exchange, those customers are subject to curtailment when power supplies run critically low, and the plan requires them to ride through system disturbances rather than disconnecting. For operators running energy-intensive facilities, this changes the tradeoff between connection speed and supply reliability.
Timeline
2020: FERC ordered grid operators to remove barriers to distributed energy resource market participation.
November 2, 2026: The CAISO board approved the large-load proposal.
November 16, 2026: CAISO is scheduled to file the proposal with FERC.
Market Landscape
The proposal follows FERC's 2020 order on distributed energy resource participation, and only ISO New England and CAISO have fully complied to date. Other regional transmission organizations and independent system operators are expected to follow in the coming months and years.
Operators planning large facilities in California should factor in the possibility of curtailment during low-supply periods when weighing an expedited grid connection. Energy-intensive businesses should review their power procurement and continuity plans with their utility and qualified advisers before the filing date.
The takeaway
The core operating insight is that expedited grid access for large loads now comes with curtailment exposure and ride-through obligations. Operators should calendar the November 16, 2026 FERC filing and track whether the proposal is modified before approval.
What happens next
CAISO is scheduled to file the large-load proposal with the Federal Energy Regulatory Commission on November 16, 2026, and the FERC show-cause response deadline falls on the same date.