Girard Avenue Construction to Begin in Early 2027
Business owners on the corridor should prepare for site access changes as the $8 million streetscape project moves forward.
Updated on Oct. 20, 2026 in Philanthropy

Live Poll
Do you support prioritizing street beautification over maintaining existing street parking in your community?
The La Jolla Community Foundation plans to start the Girard Avenue streetscape project in early 2027 following delays to reconcile divergent grant requirements. Local business owners should prepare for construction impacts as the project aims to renovate the commercial corridor with new infrastructure.
Why it matters
The project represents an $8 million investment in public infrastructure, requiring businesses to navigate prolonged construction phases while managing the complexities of combined federal, state, and private funding streams.
The $8 million streetscape project is backed by $850,000 in federal grants, $1 million from state sources, and $3 million from private donors. While phase one is fully funded, the foundation is actively fundraising for the second phase of construction.
The players
La Jolla Community Foundation
A local non-profit organization managing the fundraising and development of the Girard Avenue streetscape project.
Enhance La Jolla
An organization responsible for the management of the La Jolla maintenance assessment district.
Department of Housing and Urban Development
The federal agency providing $850,000 in grant funding toward the streetscape project.
The details
The project was delayed to ensure the design and procurement process complied with disparate federal and state grant regulations, forcing a re-bidding of the contract. The finalized plan includes 63 benches, 49 trees, 51 lights, and the addition of 9,100 square feet of public space, with stormwater drainage identified as the most capital-intensive component.
Timeline
2021: The streetscape project was initially introduced.
August 2026: Building permits for both phases were issued.
October 14, 2026: LJVMA held a meeting to discuss the project status.
October 15, 2026: Enhance La Jolla held a meeting to discuss the project status.
Early 2027: Construction is expected to commence.
Market Landscape
The project's delay due to grant compliance requirements mirrors the administrative hurdles frequently encountered when synchronizing local, state, and federal funding streams. It follows a documented trend of infrastructure projects requiring extensive reconciliation to satisfy the distinct oversight protocols of multiple government agencies.
Business owners on Girard Avenue should review their operational plans for early 2027 to account for potential street access limitations during construction. Consult with your local chamber of commerce to monitor specific site closure schedules and traffic management updates as the start date nears.
The takeaway
Large-scale public infrastructure projects often face delays when funding sources have conflicting regulatory requirements. Operators should ensure their long-term site planning allows for flexible access contingencies when relying on mixed public-private funding.
Further reading
For context on how community-led development projects are funded, see Philanthropy.
More information
View the current project plans and meeting records on the Enhance La Jolla website.
Source note: This article includes information reported by San Diego Union-Tribune.