Pipeline Easement Disputes Move to Kentucky Courts
Western Kentucky operators along the proposed gas route should plan for possible construction and supply-timeline delays.
Updated on Nov. 5, 2026 in Utilities

Live Poll
Should local governments use eminent domain to build private pipelines?
Kentucky Governor Andy Beshear said landowners opposing the Pennyrile Regional Energy Authority's proposed 53-mile natural gas pipeline can raise easement concerns in court. The project spans five western Kentucky counties and is funded by a $30 million state appropriation.
Why it matters
For operators in western Kentucky, the dispute signals that a publicly funded utility-scale gas project is now entangled in property-rights litigation, which can delay routing and right-of-way acquisition timelines. Beshear framed expanded natural gas capacity as essential for industrial recruitment, so businesses that depend on future gas supply should track whether the project proceeds on its current schedule.
The state has committed $30 million to the project, with $7 million to $8 million spent as of February according to board Chairman Eston Glover's sworn testimony. The proposed pipeline would run 53 miles across five western Kentucky counties.
The players
Pennyrile Regional Energy Authority
A regional public energy authority created by the cities of Guthrie and Trenton to develop a natural gas pipeline and distribution system in western Kentucky, with a stated goal of beginning service in 2027.
Andy Beshear
The Governor of Kentucky, who has publicly backed the project as essential infrastructure for industrial recruitment and who signed the House Bill 1 funding.
Eston Glover
Chairman of the PREA board, whose sworn deposition testimony addressed the oversight and spending of the state appropriation.
The details
The Pennyrile Regional Energy Authority was established by the cities of Guthrie and Trenton through an interlocal agreement dated June 1, 2022, approved by the Department for Local Government on June 29, 2022. Lawmakers approved the funding through House Bill 1, which Beshear signed. Beshear said good-faith negotiations are an important part of the eminent domain process, and landowners who object to easement terms can seek resolution in court.
Timeline
June 1, 2022: Guthrie and Trenton signed the PREA interlocal agreement.
June 29, 2022: The Department for Local Government approved the agreement.
September 21, 2022: Beshear announced the House Bill 1 funding during a visit to Guthrie.
February 2026: Glover testified about oversight of the state funding in a deposition.
November 5, 2026: Beshear addressed landowner concerns during his Team Kentucky update.
Market Landscape
The project is a publicly backed attempt to build regional gas capacity outside the investor-owned utility model, relying on state appropriations and interlocal agreements. Its use of eminent domain for a multi-county pipeline places it within the broader pattern of state-supported energy infrastructure that depends on land acquisition to proceed.
Businesses in western Kentucky counties along the proposed route should monitor whether easement negotiations and court challenges delay construction and the 2027 service target. Operators planning for future natural gas supply or industrial expansion in the region should factor schedule uncertainty into capital decisions and consult qualified counsel on any property or contract questions.
The takeaway
Operators in the affected counties should treat the pipeline's timeline as uncertain until easement disputes are resolved. Businesses with real estate or supply interests along the route should review their exposure with qualified counsel and watch for the state's reporting on how the $30 million appropriation is spent.
Further reading
For broader context on how energy and water service providers operate across the state, see Utilities coverage on We are Main Street.
Source note: This article includes information reported by WKDZ.