Proposed $4 Billion Gas Plant To Face Public Hearings
St. Joseph operators can weigh in on the utility project that aims to secure regional energy reliability through 2072.
Updated on Oct. 28, 2026 in Utilities

Live Poll
Should your community support new large-scale power plant construction to meet regional electricity demand?
The Missouri Public Service Commission will host public hearings beginning November 16, 2026, regarding a proposed $4 billion natural gas plant in Buchanan County. Evergy plans to build two 710-megawatt units at the site, which would support regional electricity demand.
Why it matters
Operators face potential changes to utility reliability and energy pricing as regional electricity demand prompts long-term infrastructure investment. This project signals a shift toward new natural gas generation capacity intended to secure supply for both Missouri and Kansas markets.
The proposed $4 billion facility features two 710-megawatt units, each intended to supply dedicated service areas in Missouri and Kansas. The plant is planned as a 40-year asset to address rising regional electricity demand.
The players
Evergy
An investor-owned utility providing electricity service across Kansas and Missouri.
Missouri Public Service Commission
The state regulatory agency that oversees utility rates, services, and infrastructure approval.
The details
Evergy designed the facility to include two 710-megawatt natural gas units to meet tighter regional reliability requirements. The commission process requires community feedback on environmental impacts like noise and light to determine if the project proceeds. If approved, the site would function as a long-term grid asset for four decades.
Timeline
6 p.m. Monday, Nov. 16, 2026: In-person public hearing at Missouri Western State University.
Monday, Nov. 16, 2026: Deadline to register for WebEx virtual hearings.
Tuesday, Nov. 17, 2026: Virtual public hearings via WebEx.
Spring 2032: Planned operational date for the facility.
Market Landscape
This project follows the standard review protocol required by the Missouri Public Service Commission for major utility capital expenditures. It marks a critical evaluation point for how regional power providers align generation capacity with long-term load growth.
Operators should monitor these hearings to anticipate potential long-term shifts in regional utility rates and grid reliability. Review your business energy contracts or utility provider projections as they relate to these major infrastructure updates.
The takeaway
Large-scale utility projects carry significant implications for regional operating costs over their 40-year lifespans. Business owners should track the Missouri Public Service Commission docket for final project approval status and potential rate impact announcements.
Further reading
For broader trends in power infrastructure, visit Utilities.
Source note: This article includes information reported by KQ2 | St. Joseph, Missouri News, Weather & Sports.