Casper Will Install New Hogadon Ski Lift by 2027
Casper operators should track infrastructure financing models as the city commits to a $4.1 million ski facility upgrade.
Updated on Oct. 14, 2026 in Inflation

Live Poll
Should local recreation projects be funded by user fees rather than general tax revenue?
The Casper City Council authorized the procurement and installation of a new chairlift at Hogadon Basin Ski Area. The $4.1 million project is slated for completion by the opening of the 2027-28 winter season.
Why it matters
Securing the contract now ensures fabrication lead times are met for a summer 2027 installation. The project utilizes a mix of private donations and a zero-interest municipal loan to minimize long-term capital costs.
The city has secured $3,374,500 in total funding against a $4.1 million project budget. This includes a $794,500 zero-interest state loan and a base contract of $3,323,250 that includes a 5% contingency.
The players
Casper City Council
The local governing body responsible for municipal infrastructure and budget oversight in Casper.
Hogadon Basin Ski Area
A city-owned recreational facility that serves as the primary site for local winter tourism operations.
State Loan and Investment Board
A Wyoming state entity that manages low-interest capital for local government development projects.
Friends of Hogadon
A private fundraising organization responsible for securing and transferring donor capital for facility upgrades.
The details
The city will finalize loan agreements following a transfer of donor funds from the Friends of Hogadon scheduled for late October 2026. The base contract covers manufacturing, removal of the existing lift, and installation, with $721,449 allocated for accessories. Construction is scheduled for summer 2027 to ensure the new equipment is operational for the subsequent winter season.
Timeline
2025: City established 10% Hogadon facility fee.
August 2026: City advertised request for proposals.
September 2026: City received two manufacturer bids.
October 1, 2026: State Loan and Investment Board approved loan.
Summer 2027: Construction and installation of chairlift occurs.
Market Landscape
The project utilizes a dedicated facility fee as the primary mechanism for state loan repayment. This follows the established precedent of the 10% Hogadon facility fee created in 2025 to isolate capital maintenance costs from the city's general fund.
Operators should note how the city balanced private fundraising with a zero-interest municipal loan to manage project costs without a general tax hike. Monitor upcoming bid cycles for construction and accessory procurement as potential opportunities for specialized regional contractors.
The takeaway
The project demonstrates the value of phased financing by matching private donor commitments with state-backed low-interest debt. Business owners should review their own capital procurement calendars to ensure contract execution aligns with necessary lead times for summer facility upgrades.
What happens next
The transfer of donor funds from the Friends of Hogadon to the city is scheduled for the end of October 2026.
Further reading
For more on how local governments manage large capital expenditures, see our coverage in Inflation.
Source note: This article includes information reported by Oil City News.