Long Island Gas Plants Add 1,550 Megawatts
Businesses with large power loads on Long Island should track approvals for new gas generators due between 2027 and 2035.
Updated on Nov. 4, 2026 in Utilities

Live Poll
Should new gas power plants be built on Long Island?
National Grid Ventures, the unregulated arm of the utility National Grid, has proposed three gas-powered generators on Long Island, including two at the E.F. Barrett plant in Nassau County and one at the Northport Power Station in Suffolk County. The filings were submitted to New York's grid operator in August and September, and the proposals require multiple state approvals before moving forward.
Why it matters
The grid operator increasingly views replacements as necessary amid deteriorating power plants and lagging clean energy additions, which is pushing new gas capacity onto the table even as New York targets a zero-pollution grid by 2040. For businesses in the region, the outcome will shape electricity supply and cost planning over the next decade.
The filings describe more than 1,550 megawatts of combined new gas-fired capacity across the two sites, with National Grid estimating each generator unit at roughly $1 billion nationally. The projected peak-time nitrogen oxide reduction of nearly 90% is a claim tied to the proposals, not a measured outcome.
The players
National Grid Ventures
The unregulated arm of the U.K.-based utility National Grid, which develops and owns energy generation projects outside traditional regulated utility operations.
New York Communities for Change
A grassroots advocacy organization that organized a September 2026 protest against the Northport generator proposal.
The details
Because National Grid Ventures operates as the utility's unregulated arm, it can propose generation projects that then pass through a multistage approval process before construction. Nitrogen oxide exposure is linked to asthma, heart disease, and lung damage, which is why the environmental review of replacement turbines carries significant weight. The Barrett and Northport proposals would retire aging units while adding new capacity, and a small hydrogen-fueled generator is planned for the Northport site.
Timeline
August and September 2026: National Grid Ventures submits generator proposals to the grid operator.
September 2026: Protest held in Northport, and the utility tells Newsday the first turbine likely will not arrive until the early 2030s.
End of 2027: Target opening of the first Barrett generator unit.
Late 2029: Target opening of the Northport generator.
2035: The third generator may come online.
Market Landscape
The proposals reflect a pattern in which aging thermal plants are repowered rather than retired outright while the grid waits on clean energy additions. Their path through state review will test how New York reconciles near-term reliability needs with its 2040 emissions requirement.
Businesses with large electricity loads on Long Island should track the state approval timeline and the 2027 and 2029 generator targets when projecting power costs. Operators should also monitor whether the Department of Environmental Conservation receives repowering applications, since those filings will signal how quickly capacity additions are moving.
The takeaway
The operating insight is that Long Island electricity capacity is being reshaped by retirements and replacements on a multi-year timeline. Operators should file the state approval schedule and the Northport and Barrett target dates as reference points for future supply and cost planning.
Further reading
For broader context on the state's power planning, explore Utilities coverage across New York.
Source note: This article includes information reported by The Cool Down.